When craftspersons have completed their assignments, you can enter the total hours their jobs required. Taking the time to record the hours each craftsperson spent on the job is important for tracking the cost of the job. The application uses this information to summarize costs shown for completed work in the Cost Analysis Dashboard.
If craftspersons were not originally scheduled for the job, or if additional craftspersons were needed, you can add them when updating the work request.
This topic describes updating craftsperson hours. Since having cost information is so critical to effectively managing your building operations, updating this information is a good way to get started.. If you want to see what other data you can update, and the reports that are available when you do so, see Updating Additional Information for Work Requests.
You can update a single work request at a time, or multiple requests at once. To update multiple requests, you must select only requests that are Issued and in Progress.
It can be very useful to give craftspersons the ability to update the ARCHIBUS system with details about the job. While at a job site, craftspersons will find it convenient to access and update the ARCHIBUS maintenance system directly from their smart phone or other mobile device using the ARCHIBUS Maintenance mobile app.
For example, craftspersons can access the ARCHIBUS system to put a job on hold, record the hours spent on the job, enter notes about how they resolved the problem, enter the parts used on the job, and so forth.
With the Maintenance mobile app, users at job sites do not need to use a laptop or tablet connected to the network in order to access and update maintenance information; instead, they can periodically sync their mobile devices with the server to upload the data that they record in the field, as well as download any changes from the ARCHIBUS server. See the ARCHIBUS Maintenance Mobile App.
When craftspersons log on to the Building Operations Console, they would see only their assigned work requests. The application uses the log on information to ensure that craftspersons do not see work that is not assigned to them.
Using the single-user call center approach, you could have craftspersons email you their hours, or write them on a printed work request that they bring to you at the end of the day. You can then update the work with the actual hours.
If you have scheduled the craftsperson, you can edit the craftsperson's information to add the actual hours; if not, you can add the craftsperson's hours without doing the scheduling step. This procedure describes both situations.
To update a single work request:
The Update Work Request form appears. The work is described in a read-only format at the top of the form in the Problem section.
The Date/Time assigned are entered when the work is issued, and the Estimated Hours are entered when estimating the work, so these fields are read-only.
The application summarizes the costs using the information you've entered, and shows these costs on the screen.
You can select multiple work requests and add actual hours for a craftsperson. You must be adding the same time for the same craftsperson for each work request. To update multiples, you select work requests having the Issued and In Process status.
Note: When updating multiple requests with actual hours, you are adding new records, rather than editing an existing record. For an existing record, that is a record for a craftsperson that you have assigned to the work using the Schedule action, you would edit the single record. as described in the above procedure.
To update multiple work requests:
The Update Work Requests form appears.
The Add Craftsperson form appears.
The Add Craftsperson form now shows the selected craftsperson.